Skip to content
Design free

Deck calculator

Enter the size of your deck and get what to buy: every joist, beam, post, decking board, hanger and bag of concrete, cut onto the lengths the lumber yard sells.

A 16 by 12 ft deck 36 in off the ground needs 65 boards from the lumber yard, 27 of them decking. The framing is 13 joists of 2x8 at 16 in, a 2-ply 2x10 beam and 3 posts on 3 footings. Materials come to at least $2,491 at Home Depot, Hamilton Mill store, prices read 2026-09-30 to 2026-11-04; your store may differ.
Material cost by group, some lengths estimated from the per-foot price, 1 special order line not priced (special order, price at your lumberyard)
GroupCost
Framing$417
Decking$381
Guards and stairs$548
Hardware$865
Concrete$281
Total$2,491
Lumber to buy, cut onto the lengths the yard sells
SizeLengthQtyUsed for
1x88 ft1Stair risers
1x812 ft1Stair risers
2x1016 ft2Beam plies
2x128 ft1Stair stringers
2x1212 ft1Stair stringers
2x410 ft1Guard rails
2x412 ft4Guard rails
2x416 ft3Guard rails, Stair bearing blocks, Handrail
2x610 ft1Guard cap
2x612 ft2Guard cap
2x614 ft1Guard cap
2x812 ft13Joists
2x816 ft2Rim joist, Ledger
4x416 ft3Stair posts, Guard posts
5/4x610 ft1Stair treads
5/4x616 ft27Decking, Stair treads
6x68 ft1Posts
Hardware and concrete
ItemQtyWhat to look for
Joist hanger, 2x8, at the ledger13 eaface-mount, >= 500 lb, depth >= 60% of the ledger, galvanized
Hurricane tie, joist to beam B113 ea>= 100 lb uplift and lateral (DCA6 Figure 6, Option 2)
Post base, 6x63 eagalvanized standoff post base, anchored in the footing
Post cap, 6x6 post to 2-ply 2x10 beam3 eagalvanized post cap sized to the beam width (required for 3-ply)
1/2 in x 4 in lag screw with washer12 eahot-dip galvanized; tip fully past the inside of the band; 1/2 in pilot in the ledger, 5/16 in in the band
Ledger flashing, 10 ft2 eacontinuous corrosion-resistant metal >= 0.019 in with drip edge; no aluminum on copper-treated lumber
Lateral load hold-down device2 ea>= 1,500 lb ASD, within 24 in of each deck end, into house joists or blocking
Baluster, 2x2 x 36 in, pressure-treated96 ea3-1/2 in clear between balusters (4 in sphere rule), 2 screws each end
Guard post hold-down10 ea>= 1,800 lb tension for a 36 in guard, at the top bolt, (8) SDS1/4x1-1/2 screws into 2x blocking (DCA6 Figure 25/26)
1/2 in through-bolt, nut and 2 washers, guard posts20 eatwo per guard post through the joist or rim
Deck screw, coated or stainless, #8 or #10724 ea2 per board per joist (or 2 threaded 8d nails)
Connector nails or screws260 eathe type and count each connector maker lists; never fewer
Structural screw, rim to joist ends39 ea3 per joist end through the rim
Stringer connector at the rim3 eagalvanized stringer hanger or angle (DCA6 Figure 31)
#8 wood screw, stringer to bearing block21 ea7 per stringer in Southern Pine, 11 in other species (DCA6 Commentary C12)
1/2 in through-bolt, nut and 2 washers, stair posts4 eatwo per stair post
Concrete mix, 80 lb bag28 bag2,500 psi minimum
Concrete tube form, 12 in x 4 ft5 eapier from the footing to 2 in above grade
DCA 6 table rows this deck was checked against
TableRowColumnAllowedYours
DCA 6 Table 2Southern Pine 2x816 in o.c.11'-10"9'-10 1/2"
DCA 6 Table 2 overhangSouthern Pine 2x816 in o.c.2'-0"2'-0"
DCA 6 Table 3ASouthern Pine 2-2x10joists <= 10 ft7'-9"7'-0"
DCA 6 Table 4beam span <= 8 ft, joists <= 10 ftSouthern Pine 6x614'-0"1'-6 1/2"
DCA 6 Table 51/2 in lag screw, 1-1/2 in lumber bandjoist span 8'-1" to 10'-0"18 in16.727272727272727 in
DCA 6 Table 4 footingbeam span <= 8 ft, joists <= 10 ft1,500 psf soil20 in20 in
Design this deck in 3D, free

Every setting above carries over. Not carried: the prices, which stay here. The designer sizes the footings and checks the framing against the code tables for this exact deck.

Planning figures from the AWC DCA 6-2015 guide, not an engineer's design or a permit. Your building department has the final word, and local rules may be stricter.

What the deck calculator counts

It sizes the frame first, then counts what it takes to build it. The joists, beam, posts and footings come from the AWC DCA 6 tables, so the list is for a deck that follows the guide. Then it adds the decking, the hanger and tie hardware, the post bases and caps, and the bags of concrete. Stairs and guards are counted when you switch them on.

How the boards are cut

Lumber is bought in fixed lengths, and the calculator packs each cut onto the shortest board that holds it. The list you see is what you would carry out of the yard, not the raw footage. A saw kerf is allowed for between cuts.

Prices

Cost uses shelf prices read at The Home Depot, Hamilton Mill, on 2026-09-30. Prices differ by store and week.

Our cost to build a deck guide prices four standard sizes in wood and composite and sets them beside the installed ranges the cost sites publish.

What it does not count

Lights, permits, tools, delivery, sales tax, and any site work or digging. Treat the count as the starting point for your shopping list and ask the yard for an extra board or two for mistakes.

Where the numbers come from

Every limit on this page is read from the American Wood Council, Prescriptive Residential Wood Deck Construction Guide (DCA 6), 2015 edition, a guide written for the 2015 International Residential Code. The deck designer, the builder's plan and these tools all read the same tables. The span tables assume 40 psf live load, 10 psf dead load, No. 2 grade lumber in wet service, and footings on soil that bears at least 1,500 psf.

A number that is our own choice and not in the guide, such as the 24 in joist overhang we draw by default, is never presented as a code requirement. Where a value comes from somewhere other than DCA 6, the page says so.

More free calculators

  • Joist span

    The smallest joist that spans your distance, and how far it can overhang.

  • Beam span

    How far apart the posts can be for a 2-ply or 3-ply built-up beam.

  • Stair stringer

    Steps, riser and tread sizes, stringer count and board length from a total rise.

  • Deck footing

    Footing size, depth and concrete bags for the whole deck.

  • Pergola span

    How far a pergola beam and rafters can span, and what limits them.

  • Paver calculator

    Pavers, gravel base, sand, edging and polymeric sand for a patio.

  • Concrete slab

    Cubic yards, 80 lb and 60 lb bags, gravel, mesh and control joints for a slab.

  • Span tables

    The joist, beam and post tables from DCA 6, by species and spacing.

Questions

Anything else? Write to us or see every calculator.

Questions people ask

We do not quote labor, because it swings with the region, the height and the contractor. Our calculator counts the materials, so you can price the same list from your lumber yard and hold any contractor's bid up against it. If you hire out the build, ask for materials and labor as separate lines.

The decking and the frame are the two big lines, and which is bigger depends on the boards you pick. For a 16 by 12 ft deck at 36 in, our count is 27 decking boards and 38 boards of framing and other lumber, before hardware and concrete. Switch the decking above between wood and composite to see how the count and the boards change, then price each line at your own yard.

Divide the length of the deck, measured across the boards, by the board width plus the gap, which is 5.5 in plus about 1/8 in for wood, to get the number of rows. Then cover each row with boards from the lengths the yard sells, 8, 10, 12 or 16 ft, so the cuts waste as little as possible. The calculator does this packing for every board in the deck, joists and beam included.

Yes. It counts the ledger, joists, beam, posts, the concrete for the footings, joist hangers, post bases and the fasteners. Stairs are optional, and guard rails are added on their own once the deck is more than 30 in above grade. Boards are bought in 8, 10, 12, 16 ft lengths, and longer special-order boards only where a piece cannot be spliced.